| Component | % Weightage as per Schedule – G | Physical Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
|---|---|---|---|
| Road Works i/c Culverts, Minor Bridges, Underpasses & Approaches | 60.06% | 3.11 % | 35.56 % |
| Major Bridge Works & ROB / RUB | 1.42% | 0.12 % | 0.78 % |
| Structures [ Elevated Section | Reinforced Earth] | 12.75% | 0.49 % | 5.83 % |
| Electrical and public health utilities | 2.10% | 0.00% | 1.53 % |
| Other Works | 23.67% | 0.87 % | 2.14 % |
| Total | 100% | 4.60 % | 45.84 % |