Physical Progress

Physical Progress

Component % Weightage as per Schedule – G Physical Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road Works i/c Culverts, Minor Bridges, Underpasses & Approaches 60.06% 3.11 % 35.56 %
Major Bridge Works & ROB / RUB 1.42% 0.12 % 0.78 %
Structures [ Elevated Section | Reinforced Earth] 12.75% 0.49 % 5.83 %
Electrical and public health utilities 2.10% 0.00% 1.53 %
Other Works 23.67% 0.87 % 2.14 %
Total 100% 4.60 % 45.84 %