Particulars | Details/Status |
---|---|
Project Name | 4-Four Laning of NH 530B from Devinagar Bypass (End) (Existing Km. 208.000 of NH 530B/Design Km. 66.000) to Kasganj Bypass (End) (Existing Km. 150.100 of NH 530B/Design Km. 123.100) in the State of Uttar Pradesh on HAM mode |
NH No. (New/old) | NH-530B |
Mode of Execution | Hybrid Annuity Mode (HAM) |
Concessionaire Name | M/s GR Devinagar Kasganj Highway Private Limited |
Date of Letter of Award (LOA) | 29.03.2023 |
Appointed Date | Yet to be Declared |
Construction Period (in Days) | 730 Days from the Appointed Date |
Schedule Completion Date | 730 Days from the Appointed Date |
Operation & Maintenance Period | 15 years from COD |
Independent Engineer | M/s URS Scott Wilson India Pvt Ltd, In Joint Venture with Almondz Global Infra Consultant Ltd. |
Authority Name | National Highways Authority of India, PIU-Badaun |
Independent Engineer Mobilization Date | Yet not mobilized |
No. of Lanes/ Configuration | 4/6 Lane |
Bid Project Cost | 1226.87 Cr. |
Total Length of the Project | 57.967 km (CA) / 58.342 (Design) |
No. of Elevated Viaducts | 04 no. |
No. of Underpasses | VUP-10 no., LVUP-01 nos. |
No. of Major Bridges | 01 nos. |
No. of Minor Bridges | 23 nos. |
No. of Culverts | 82 – Box Culverts 30 –Pipe Culverts |
Toll Plaza | 01 nos. |
Rest Area | 02 nos. |